The following data relate to direct materials costs for February: Materials cost per yard: standard, $2.00; actual, $2.10Standard yards per unit: standard, 4.5 yards; actual, 4.75 yards Units of production: 9,500 Calculate the direct materials quantity variance.

  

The following data relate to direct materials costs for February: Materials cost per yard: standard, $2.00; actual, $2.10Standard yards per unit: standard, 4.5 yards; actual, 4.75 yards Units of production: 9,500 Calculate the direct materials quantity variance.

a.$4,750.00 unfavorable

b.$4,750.00 favorable

c.$4,512.50 favorable

d.$4,512.50 unfavorable