Given a project salary cost of $400,000 per year and forecasted wage increases of 5 percent per year, calculate the no discounted total

  

1 Given a project salary cost of $400,000 per year and forecasted wage increases of 5 percent per year, calculate the no discounted total
salary cost over a three-year project lifecycle. (Points : 1) $400,000
$420,000
$1,261,000
$1,652,400

2. You have been asked to estimate the costs for a project to build an industrial power plant. Based on
historical data, the steam turbine accounts for 30 percent of the total costs for the plant. If the steam turbine costs
$300,000, the expected top-down estimated cost for this project would be __________. (Points : 1)$500,000
$1,000,000
$1,300,000
$1,500,000
3. A work element in the project plan requires 50 hours of labor each by four carpenters. The carpenters are
paid $15 per hour and incur an overhead rate equal to 80 percent of their direct labor charges. Based on this data, the
appropriate cost is __________. (Points : 1)$750
$1,500
$3,050
$5,400
4. A cost estimate for a given project activity is $6,300; this cost estimate does not factor in personal
time. Assuming that an allowance for personal time is 9.5%, the total estimated cost of the project activity including personal
time is approximately: (Points : 1)$6,300
$6,899
$6,990
$7,300